Silo collapse results in load shedding across South Africa

Posted On Monday, 03 November 2014 08:53 Published by
Rate this item
(0 votes)

Power utility Eskom says there will be load shedding across South Africa from Sunday.

 

Tshediso Matona Eskom

Wednesday evening and the whole of Thursday are marked as high risk for power cuts.

This after one of the three silos, which housed over 10 000 tons of coal each, cracked and later collapsed at Majuba power station on Saturday, impacting coal supplies to six units. The Utility's Chief Executive Tshediso Matona on Sunday said no injuries were reported following the incident.

He said all units were running normally, prior to the silo collapse, but at approximately 12:30 one of the staff members at the station reported a visible crack on silo number 20. He said the crack on the silo enabled personnel on the station site to be evacuated. The crack was later followed by a collapse.

"The area was immediately secured and protected," he said. Matona said the station output was immediately affected and reduced from 3 600 megawatts to 18 00 megawatts and the situation worsened afterwards. "We are now sitting at capacity output of 600 megawatts," he added.

Investigations and inspections

Matona said Eskom engineers are investigating the cause of the incident and results will be communicated in due cause. "The latest civil-visual inspection that was conducted in September 2013 found that the concrete structure was in good condition," he said.

He added that there was some external damage which was attended to and that risk classification at the time was classified as low. The other two silos remaining at the power station will not be operational as they also undergo inspection.

"The cause and costs of the incident are yet to be investigated," he said.
He said the situation is being monitored constantly and the public will be updated on progress, both on the incident and contingency plans.

Contingency measures

"We do not think we will be able to recover all the capacity, but our aim is [over the next couple of days] to make sure that we recover as much lost capacity as possible," he said. He said the success thereof will depend on logistic arrangements to feed coal to the units.

Eskom said it will in the meantime make use of mobile coal feeders at the station, as one of interventions to recover lost capacity. Meanwhile, the public is urged to switch off pool pumps, turn air-conditioning to 23⁰C and to switch off geysers and unnecessary lights to limit the impact of the load shedding.

He said Eskom will keep the public updated about any developments and information regarding load shedding. The power cuts will rotate across the country, and the load shedding schedule is available at http://loadshedding.eskom.co.za/ for Eskom customers

Most Popular

Residential sectional title sales again on the rise

May 27, 2021
Andrew_Golding_Golding_PropertyGroup
Over the past 15 years, the sectional title market in South Africa has become entrenched…

Pick n Pay and Fortress co-invest in a super distribution centre development

May 26, 2021
Fortress_Pick_n_Pay
Fortress REIT announced that their biggest logistics development to date was signed with…

Ongoing property market uncertainty makes the right finance partner key to extracting value

May 26, 2021
Claire Denny
Results from the listed property sector in 2020 showed property values reducing by an…

East Rand Mall will soon deliver the first phase of its major taxi rank upgrade

May 26, 2021
Phase 1 upgrade to the taxi rank at EastRand Mall
The first-phase upgrade of East Rand Mall taxi rank in the retail heart of Boksburg,…

Insurance policy renewals – the devil is in the details

May 27, 2021
PJ_Veldhuizen
Although your insurance policy should be reviewed annually, by paying your insurance…

Please publish modules in offcanvas position.