OR tambo's R17bn facelift

Posted On Wednesday, 10 March 2010 02:00 Published by eProp Commercial Property News
Rate this item
(0 votes)

About 90% of the R17 billion upgrading at the OR Tambo International Airport for the 2010 Fifa World Cup has been completed.

Chris HlekaneAbout 90% of the R17 billion upgrading at the OR Tambo International Airport for the 2010 Fifa World Cup has been completed.

Most of the remaining work will be completed this month and some in April, OR Tambo International Airport (Ortia) general manager Chris Hlekani said.

He said the remaining infrastructural work at Ortia was the completion of a multistorey parkade and two fuel tanks by the end of this month.

Also the completion of seven aircraft apron stands by next month.

After the upgrades the airport's central terminal building, which was completed in December, will have the capacity to handle about 28 million passengers a year.

There will be 16 500 parking bays, 105 aircraft stands and a jet fuel storage capacity of 60 million litres.

Hlekani said all operational plans would be finalised by May 14. About 450 000 passengers are expected to travel through the country's airports during the six-week tournament, that starts on June 11.

Acsa group manager for operations André Vermeulen said between 45 and 46 slots an hour were used at Ortia, and the company had already received applications from commercial and non commercial airlines for an additional 120 000 slots above the normal slots during June and July.

Hlekani said Acsa planned to operate on a 24-hour basis as per match schedules and was in the final stages of negotiations with the Department of Labour.

He said Acsa was also engaging with bus and taxi transport operations to finalise transport operations at airports for the event.

Hlekani said Acsa was busy training workers in customer care programmes that includes basic language training in Spanish, French, German and Italian.

Other airport upgrades

Acsa was also planning to establish a specific terminal for the exclusive use of the teams taking in the sporting event in one of the cargo areas of the airport.

The area will incorporate a public viewing area.

Hlekane noted that similar plans were being considered at the other airports around the country.

At Cape Town International Airport the central terminal will be completed by the end of this month, increasing capacity to 14 million passengers a year.

Further, the completion of a multistorey parkade would boost parking to 8 000 bays.

The construction of an additional five aircraft apron stands, to be completed next month, will result in the availability of 32 aircraft stands.

King Shaka International Airport, in KwaZulu-Natal, will start its commercial operation on May 1.

The airport will have the capacity to handle 7,5million passengers a year.

The upgrades of the Bloemfontein airport terminal were completed in December, while the East London terminal and Kimberley terminal will be completed by the end of this month.

The Upington airport terminal's upgrade will be completed next month.

The development of two temporary terminals at the Bloemfontein and at the Port Elizabeth airports will both be completed by May.

The temporary buildings costing a collective R8,9 million can each handle an additional 350 passengers an hour.

This will allow for the airports to overcome the capacity constraints in terms of handling the peak traffic during the early part of the 2010 Fifa World Cup.

 

Last modified on Wednesday, 30 October 2013 21:18

Most Popular

Should you rent or buy your business premises?

Jun 23, 2022
Malusi Mthuli_FNB
This is a question that most business owners will face at some point in their journey.…

April 2022 Hotel Accommodation Income Statistics continue to show a very weak picture compared to pre-lockdown times.

Jun 23, 2022
Hotels Monthly Income 2022
The StatsSA release of April 2022 preliminary monthly tourism statistics show the Hotel…

South Africa’s inflation exceptionalism: can it last?

Jun 23, 2022
Carmen Nel
South Africa is often seen as a high-beta play, be it regarding financial market risk…

Hyprop continues to reduce debt and reposition its portfolios in SA and EE

Jun 30, 2022
Skopje City Mall Playground
Hyprop, which manages dominant retail centres in mixed-use precincts in key economic…

Vaal Mall rolls up its sleeves for pothole repairs

Jun 30, 2022
Vaal Mall crew busy repairing the various potholes making easier access to the Centre.
Vaal Mall is showing their commitment towards their community by stepping up to repair…

Please publish modules in offcanvas position.